Home » Case Studies » Homewood Farm Solar – local supply scheme

Homewood Farm Solar – local supply scheme

Project Summary

Homewood Farm is a solar ground mount proposal with the potential to directly supply the local community with solar generated energy via a local supply scheme.  

Background

In 2019 two parish councils near Bath commissioned Bath and West Community Energy (BWCE) to investigate potential Solar PV locations. These included a previously identified site at Homewood Farm, Freshford. 

Terms were agreed in principle with the Homewood farm landowner and a 12-month exclusivity agreement was signed. A low voltage grid connection, suitable for local supply, was secured with Scottish and Southern Electricity Networks (SSEN). 

Results and outcomes

BWCE received Community Energy Fund (CEF) Stage 1 grant funding of £39,966 from the South West Net Zero Hub to develop the Homewood Solar Farm project.  

 Key tasks carried out: 

  • Ensure technical feasibility
  • Fully understand the local supply model  
  • Ensure the projects commercial viability 
  • Ensure there were no major planning or legal issues 
  • Ensure secure grid connection suitable for a local supply model 
  • Engage with the local planning authority via pre-app
  • Conduct non-site-specific community engagement
  • More site-specific community engagement was carried out than originally planned

As a result, the project was able to ensure technical feasibility.  

BWCE have now applied for CEF Stage 2 funding (£99,916) which will support the project up to a full planning submission.

Lessons learnt

After the project was announced in a parish council meeting, residents had some questions which could not be answered before feasibility work was complete.  

As a result, BWCE began early engagement with the local community at parish council meetings, through home visits, and drop-in events.  

Through this site-specific community engagement, BWCE were able to better understand local opinion – positive and negative – and address issues at an early stage which helped to build trust within community. 

Community benefits

  • An annual ring-fenced benefit to the communities local to the solar farm.
  • Potential to support 300-500 households (assuming a local supply model and subject to uptake) 
  • Surplus income from the solar farm returned to the community pot and distributed via a grant scheme to eligible projects in the area.  
  • If a local supply model is adopted, local club members will be able to purchase energy directly from the solar farm when it is generating, at a special local power tariff rate. 

Wider benefits

  • Number of Households supported (potential) 300-500 (assuming a local supply model and subject to uptake) 
  • A community owned project, putting local people in control. Local residents can invest, become BWCE members and have a vote.
  • Community energy projects typically deliver 10 times the community funds proportionately compared to similar commercial schemes
  • BWCE aim to deliver a minimum 25% biodiversity net gain, enhancing the habitat and leaving it in a measurably better condition 
  • Potential to create 19 jobs (projected estimate) 

Funding and investment

Community Energy Fund Stage 1 grant £39,966

Community Energy Fund Stage 2 grant £99,916

Next steps

The next stages of the project to be funded by the CEF Stage 2 grant: 

  • Complete remaining planning surveys and submit full planning application;  
  • Conduct further community engagement  
  • Promote the local supply model and gauge the level of interest from local residents 
  • Complete a site-specific survey 
  • Develop the design and financial modelling  
  • Further engage with the DNO (SSEN) to ensure milestones are met.  

BWCE plan to submit a full planning application during 2025 and commence installation in 2026.  

Key facts

Community Energy GroupBath and West Community Energy
Project LocationFreshford near Bath
Community Energy Fund Priorities Supported* Building Resilience in Communities  
* Reducing Carbon Emissions  
* Lowering Energy Costs  
Energy generation/saving800kWp (solar)  
Energy/Heat Actual generated 842,000kWh/annum
TimelineInstallation in 2026 (subject to planning permission) 
Carbon saving 160 tonnes per annum 
Project value £903,000 including development and installation (estimated total)
Project website Find out more on the BWCE website